Roundhouse build
During 2018 Chris and Michelle photographed, blogged about and diarised the Roundhouse build. Hover over the pictures to find out more. If you would like to find out more about our Roundhouse build you  can contact Chris at mailto:[email protected]
9000 wine bottles - Required for Roundhouse foundations * 350 Whistlewood shareholders div. by time = 2 bottles each per week. Local pubs & restaurants asked to help * Are they strong enough to hold up a floor - they are designed to withstand pressure that builds inside. Will help with insulation in the Roundhouse. Let's get Drinking!
Community is our backbone - Can only build the Roundhouse because of the community that has built and loves Whistlewood * Won grants to show its value to the community * Companies have overwhelmed us with their generosity * Shareholders made up of not just individuals but communities such as WIs, Schools, etc
The first little pig - certainly Buildings Control are not used to straw bale buildings! So does straw work? Yes - with the right compression and building design. * Will it pass safety regs - Yes, professional, experienced builder. Signage inside etc complies. Fire regs - compressed straw breaks the fire triangle, starving the bales of oxygen * But still breathable
Whistlewood track - no building is an Island! How will we get heavy vehicles to the Roundhouse build from the gate? Track - 90 metres long, 3.7 metres wide with all weather parking * Turning circle with 2 disabled places widens to 6 metres at Hub gate which will have vehicular and pedestrian entrances
Rain, rain, go away - stuck in the mud at the mo * Planning build, equipment we would like to borrow * Build partners to complete track, volunteers to set up site. Track and building site have to meet Health and Safety regs * Selecting trees at Staunton Harold estate for support posts
First cut - Track work started * Envisaged to take 16 weeks * Enough bottles collected * Schedules slipped due to weather, new ideas & supply problems * Blocks instead of tyres for the foundation due to lack of time
Build diary wk 1 - Trench and block work * The team from Dales Contracts start * Excavation to create trench in which Roundhouse will be built * Shallow, circular trench filled with limcrete * Blocks built up 5 courses, for the wooden base plate
Build diary wk2 - Gaining some height * Wooden base plate fixed in place * Pipe installed for Wood-burning stove * Locally sourced Hazel Stakes created for stabilization of straw bale walls * Main entrance door framed * Followed by 3 other âstageâ doors * Short hazel stakes fitted, then first straw bale
Build diary Wk 3 - local timber * First bale to last bale in 4 days! * Long hazel stakes pinned down through them for stabilization * Volunteers debark larch poles that will form supports for the verandah
Build diary wk 4 - Putting up scaffolding * Remaining timber debarked ready for âcertificationâ * âPadsâ prepared for larch poles
Build diary wk 5 - ready to squeeze * Timber certification completed * Second Buildings Inspection visit * Track completed * Painting the steel supports * Timber top plate installed on bales
Build diary Wk 6 - its got a top * Top wall plate filled with straw & finished with OSB * Knocking bales to straighten them â with a âpersuaderâ * Compression process completed with lorry straps â 70 mm total * Main compression ring arrives â sits on top of the bales & supports the roof rafters * Craning in ring beam * Rafters are bird-mouthed
Week 7 - ready to shingle - Installing ânogginsâ for roof lights * Installation of the felt (waterproof, breathable membrane) * Installation of lathes to take cedar shingles * Applying Danish oil to the Ring beam * Installation of the first structural roundwood poles for the external walkway
Week 8 - Shaping up nicely - Structural Roundwood poles all in position and walkway rafters * Three metre wide roof will be created for the verandah
Week 9 - batten down the hatches - Finishing off the roof rafters of the verandah and filling in with OSB board which goes under the GRP waterproofing that is then under the living roof matting * Dealing with the awkward angles of an octagonal building * Cover with tarpaulin
Week 10 - got a lot of bottle - Trimming and âpersuadingâ of the inside strawbale walls, stuffing holes with straw * Internal scaffolding was removed * Internal Floor raised by 50mm then geotextile membrane laid down * Weekend - the great bottle installation! * Nearly completed in one day but we ran out of sand
Week 11 - limecrete floor - More sand installed and bottle insulation layer completed * Another layer of geotextile laid on top of the bottles * Locate the circular shuttering (right in the middle) to take the central feature tile floor * Then limecreting the floor * Once dry the circular shutter was removed * Working on the roof lathes
Week 12 - under wraps - Further work on the lathes and the fascia boards on the end of the roof rafters * Concentrating on one internal wall that will take shelves for a library of books * Involves fitting OSB strips and hazel stakes * Installing âfirst fixâ electrical cables
Week 13 - ready sedum go - Cracking on with the verandah roof fitting GRP (Glass Reinforced Plastic) waterproofing applied * Followed by a colooured (grey) resin * Building a box to house the solar panel battery
Week 14 busy, busy, busy - Openings created for the velux windows * Installing fibre board internally on the gap * Up to the rafters to accommodate the internal clay rendering * Similarly on the external walls fibre board installed and base layer of lime render applied
Week 15 - up on the roof - Shingle laying * Velux Window installing * Finishing off the âservicesâ box * Applying the external limecrete coats * First Layer â lime plaster with hemp * Second - lime plaster with horse hair
Week 16 - mud, mud, glorious mud - External final layer of lime render * Installing the foundation pads for the main decking supports * Second coat of clay render to the inside * Installing a Truth Window to show the construction of straw * Further work on shingles including a joint between shingle roof and sedum called a (lead) âsoakerâ
Week 17 - we have the support - Installing the deck substructure * Remove the Scaffolding * Doors were installed * Decking started
Week 18 - Glazed expression and a woolly mind - Doors glazed * Decking sections completed * Lantern arrived and assembled * More shingles on the roof * Insulating the roof inside with sheepâs wool insulation
Week 19 and 20 - warm, dry and well plastered - Roof insulation plastering * Lantern Installation * Shingle roof completion
Week 21 - hole in the ground, so big and so round - Completing the clay rendering inside * Cutting a drainage channel * Making the footings for the verandah and stage * Water tank installation
Week 22 - all decked out (almost) - Decking support finished to form the stage * Top boundary to the sedum roof put in place and back-filled with pebbles * More boarding for the stage
Week 23 - three chains, drains, decking - Installing the galvanised guttering, downpipe and chains * Finishing off the stage * Saying goodbye to the builders!